Yukon Engineering Services involvement in the Minto property dates back to the early 90’s under previous ownership. YES was involved in the development of the Minto Mine, which included all surveying, mining contractor payment determinations, and layout of Water retention Dam, roads, ditches, and open pit layout. Onsite and head office support for progress estimates and varios road and pad designs. 

Scope of the Work

All surveys for design
Construction layout
Quantity determination
Design services for on site civil (dams, roads ponds, and pads)
Maintain status map and status data base

People Involved

Jerry Quaile - Project Designer
Gary Birckel, A.Sc.T. - Field Surveys and CAD
Kyle McLaren - Field Surveys and CAD
Marshall Hatton, EIT - Field Surveys and CAD
Greg Cooper - CAD Leader
Rob Harvey - Internal Review
Sylvain Lessard, CLS, M.Sc. - Internal Review

Prime Consultants

JDS Consulting Ltd. (Mine Development Project Management)
Hatch, JDS Consulting Ltd. External Review
Access Consulting Group Environmental

Top of the page image

In Loving Memory

Rob Harvey

1955 - 2007
A man with Vision and Innovative Ideas

"Whether you agreed or disagreed with him, Rob had a way of making you think."

Designed by: Polar Hosting & TNTStudio